Shijiazhuang Heping Road Viaduct | China

Project Description
Heping Road Viaduct Steel Box Girder Project - Shijiazhuang City
The Heping Road Viaduct Project in Shijiazhuang City is a key urban overpass crossing the Beijing–Guangzhou Railway Line. The bridge adopts a two-span continuous steel box girder structure with a total length of 128.452 meters, designed to meet strict safety and operational requirements for railway crossings.
The superstructure is a single-box multi-cell steel box girder with a top width of 25.5 meters, providing high torsional rigidity and overall structural stability. The steel box girder design is well suited to accommodate wide bridge decks, complex alignments, and varying cross-slope conditions commonly found in urban viaducts.
The horizontal alignment consists of an 800-meter-radius circular curve combined with a transition curve and a straight section. The bridge deck cross slope transitions smoothly from a 3% unidirectional slope to a 1.5% bidirectional slope, placing high demands on fabrication precision and geometric control during manufacturing.
To minimize disruption to railway traffic, the bridge was assembled parallel to the railway alignment and then rotated into its final position as a whole. The entire bridge rotation was completed within one hour, demonstrating efficient construction coordination and reliable structural performance. This project highlights strong capabilities in large-width steel box girder fabrication and support for complex urban bridge construction methods.

.jpg)
.jpg)
■ The project is located in Heping Road, Shijiazhuang city, across the Beijing-Guangzhou railway line.
■ Two-span steel structure continuous steel box girder, the total length of the bridge is 128.452m.
■ The bridge structure is designed as a single box multi-compartment steel box girder with a single box roof width of 25.5m.
■ The horizontal projection line of the bridge is an 800-meter radius arc + easing curve + straight section.
■ The transverse slope of the bridge deck changes from 3% one-way slope to 1.5% two-way slope.
■ After assembling in the direction of the railway, the whole construction should be carried out in a flat way, and the rotating work should be completed within 1 hour.
Contact Us
Building Global Landmarks
with China's Steel Excellence













English
Français
Deutsch
Português
Español
русский
한국어
العربية
Italiano
Indonesia
Schweiz
Polski
Nederlands
ישראל - עברית
Perzisch
ไทย
日本語
ኢትዮ-አማርኛ
Việt Nam
Kiswahili
Srpski
Ελληνικά
简体中文

.jpg)